Kapichira Rehabilitation Work Start Next month

Kapichira Rehabilitation Work Start Next month

Local, Uncategorized
There are now hopes for improved power outages in Malawi as power generator EGENCO has disclosed plans to commence reconstruction works for Kapichira power station in July. This follows securing funds amounting to 60 million US Dollars from World Bank through the Ministry of Finance for the repairs of the Kapichira dam for both phase 1 and phase 2 works. The funds are to cater for the Emergency Power Restoration Project from cyclone Ana disaster for both EGENCO and ESCOM. In a statement released by EGENCO, the first phase of rehabilitation works will involve temporary reconstruction of the dam to resume power generation with the actual works commencing on 1st July and will take 3 to 4 months to be completed. The second phase which will involve construction of a resilient-perma...